Work Planned upto 27/02/2010 |
Completad / Progress |
Remarks |
Staging work for P3-P4 Span |
Not started |
|
P4-P5 Span Staging work removal |
In Progress |
|
Concreting girders - 3 nos. |
Completed |
|
Stressing girders |
Completed |
|
Shuttering work for cross beam & slab |
Completed |
|
Reinforcement work for slab |
In Progress |
|
Approval of GAD by railways- follow up to be |
|
Delay in GAD approval |
done by contractor |
|
|
Box culvert works (under pass) |
Not started |
Contractor agreed to start under pass, water line and telephone line to be shifted for excavation |