Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7888527
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 11.11.2011
    
 

Description

Completed/ Progress

Remarks

ROB at Parappanangady

 

 

Pier cap (Total no of pier Cap- 21)

Completed

19 NOS COMPLETED

RE Wall panel casting ( total 550 nos)

Completed

 

Slab calicut side  (total 10 nos )

In progress

9nos done

slab NH side ( 11 nos)

In progress

10 nos done

Retaining wall NH side

In progress

Done LHS -90%, RHS- 90%

Dirt wall AP1 concreting

In progress

Done 90%

Handrail casting

In progress

720 nos completed.

Handrail fixing

In progress

NH side 1 slab completed.

Boring at RP1,RP4

In progress

 

NH side RE panel erection

In progress

0.4% completed.

RE wall excavation Calicut side

Completed

Foundation design should summit by contractor.

expansion joint NH side completed

In progress

9 nos completed.

 

 
Back
 
    
REINFORCEMENT FOR PILE.

    
    
RE WALL WORK-NH SIDE.

    
    
PILING WORK IN RP1.

    
    
HANDRAIL FIXING.

    
 
    
HANDRAIL FIXING IN AP2-P19 SLAB

    
    
EXPANSION JOINT CONCRETING.

      
 

 

 

 

 

 

 

 

Untitled Document