Description
|
Completed/ Progress
|
Remarks
|
ROB at Parappanangady
|
|
|
Pier cap (Total no of pier Cap- 21)
|
Completed
|
19 NOS COMPLETED
|
RE Wall panel casting ( total 550 nos)
|
Completed
|
|
Slab calicut side (total 10 nos )
|
In progress
|
9nos done
|
slab NH side ( 11 nos)
|
In progress
|
10 nos done
|
Retaining wall NH side
|
In progress
|
Done LHS -90%, RHS- 90%
|
Dirt wall AP1 concreting
|
In progress
|
Done 90%
|
Handrail casting
|
In progress
|
720 nos completed.
|
Handrail fixing
|
In progress
|
NH side 1 slab completed.
|
Boring at RP1,RP4
|
In progress
|
|
NH side RE panel erection
|
In progress
|
0.4% completed.
|
RE wall excavation Calicut side
|
Completed
|
Foundation design should summit by contractor.
|
expansion joint NH side completed
|
In progress
|
9 nos completed.
|