Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7888580
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 11.11.2011
    
 

SlNo

Activity –which can be completed without caution

Description

Total Quantity

Cumulative progress up to this week

(1)

Balance  work

(2)

Cumulative delay in weeks after

Spplagmnt

(3)

Work  planned  during the week

(4)

Actual work done during the last week

(5)

Short fall in the last week 

(6)

Work 

Planned for next week

(7)

No of days remaining for completion as per the weekly plan

1

Re wall towards NH side

100%

34

66

32

 

 

0

0

 0

3

Approach

 Span

 

5

 

5

0

37

-

-

-

-

 

4

Pier cap

2

2

0

46

 0

 0

 0

 0

 0

5

Pile (Rly)pulikakadavuside

4

 

4

0

60

 0

 0

0

6

Pile (Rly)Nhside

4

4

0

60

0

0

0

0

0

6

Piers (Rly)

 

2

2

0

51

 0

 0

 0

 0

 

9

R0AD WORK

{WBM} towards pulikkakadavuside

100%

90

 

0

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1O

Kerb/handrail  (approach portion)N.H side

200m

Inner kerbconcreting complete for a distance of  25 metres.Handrailposts  concreted for a. distance of 50 metres.Nowork in the last week.

 

Nil

 

 

 

 

 

12

Friction slab  approach portion(N.H side

200m

 

No work in the last week

 

 

 

 

     

 

 

 

Material Stocking Status

 

 

Coarse Aggreagate (m3)

8

9

Fine Aggreagate(m3)

 5

 8

Cement(bag)

 9

 12

Steel(MT)

 6

5

 RE blocks

 2150 available at site

  

 

Utility shifting

 

 

Utilities to be shifted

Status

Remarks

BSNL

 

 

KSEB

 nohindrance

 

KWA

 

 .

Others

 

No hindrance

  

Climate & Labour

 

DATE

5-11-2011

6-11-2011

7-11-2011

8-11-2011

9-11-2011

10-11-2011

11-11-2011

Weather

sunny

Sunny

Sunny

Sunny

Sunny

Cloudy

cloudy 

Labour 4 5 4 4 5 5 5

 Daily activity report

Sl.

No

Date

Activity

1

5-11-2011

Pile cap reinforcement at P8

2

6-11-2011

Pile cap reinforcement at P8

 

3

7-11-2011

Pile cap reinforcement at P8

 

4

8-11-2011

Pile cap reinforcement at P8

 

 

5

6

  

7

 

 

9-11-2011

10-11-2011

 

11-11-2011

Pile cap reinforcement at P8

Pile cap reinforcement  and shuttering at P8

 

Pile cap reinforcement  and shuttering at P8

 

  

•Concreting of the Pile  P8(5) , P8(3),P8(2),P8(1),P8(4) completed.
•Heavy rain affecting the progress of work
•Concreting of  pile cap at P8 planned for the next week.
•Reinforcement work of pile cap at P8 in progress
•Caution not yet obtained to start piling work at P7 location 

 

 
Back
 
    
SHUTTERING WORK OF PILE CAP COMPLETE

    
    
PILE CAP SHUTTERING AT P8

    
    
PILE CAP SHUTTERING AND REINFORCEMENT IN P8 LOCAION

    
    
PILE CAP REINFORCEMENT AT P8

    
 
    
PILE CAP REINFORCEMENT AT P8.

    
    
PILE CAP REINFORCEMENT AT P8 LOCATION

      
 

 

 

 

 

 

 

 

Untitled Document