   Weekly progress report as on 11.11.2011
    
 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

1

PILE SHORNUR  SIDE

9

9

 

 

 

Completed

 

 

 

2

PILE M.C SIDE

36

36

 

 

 

Completed

 

 

 

 

3

PILE CAP SHORNUR SIDE

3

3

 

 

 

Completed

 

 

 

 

4

PILE CAP  M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

5

PIER SHORNUR  SIDE

3

3

 

 

 

Completed

 

 

 

 

6

PIER M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

7

PIER CAP SHORNUR  SIDE

3

3

 

 

 

Completed

 

 

 

 

8

PIER CAP M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

9

RE/R WALL SHORNUR SIDE

100%

39

61%

0

10.00%

5.00%

63.00%

10.00%

0

RCC wall second  lift concreting completed on one side.i.e (13 metres ).RCC wall concreting opposite side of shornur side (first lift) - 5 metres completed.

10

RE/R WALL M.C SIDE

100%

9

91%

0

5.00%

0.00%

13.00%

5.00%

0

No work has been possible in the RE wall portion due to heavy rain  and wet soil.PCC for RE wall portion to be laid today

11

BEAM/SLAB SHORNUR  SIDE

3

2

1

0

0

0

0

0

0

 

12

BEAM/SLAB M.C SIDE

12

11

1

0

1

1

0

0

0

deshuttering of the span P5-P4 in progress

13

HR/FP/KERB SHORNUR  SIDE

100%

50

50%

0

0.00%

0.00%

0.00%

0.00%

0 days

 

14

HR/FP/KERB M.C SIDE

100%

53

47%

0

8.00%

1.00%

6.00%

8.00%

 

Inner kerb concreting completed on both sides od P7-P8.Footpath slab concreting  at P12-P13.Expansion joint work completed at P5

15

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

  

 

Availbility of Men               
Date 11-05-2011 11-06-2011 11-07-2011 11-08-2011 11-09-2011 11-10-2011 11-11-2011
Nof labours 18 18 18 18 18 18 18 

 

Material Stocking Status          
  Required Available Remarks    
Fine aggregate {cft} 300 300      
Cement(bag) 300 126 stock will be replendished soon    
Steel inT 11 12      
Coarse Aggreagate (cft) 300 200      

 

Utility shifting  
Utilities to be shifted  
BSNL COMPLETED
KSEB COMPLETED
KWA COMPLETED
Others COMPLETED 

 

 