Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8051359
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 11.11.2011
    
 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

1

PILE KAINATTY  SIDE

18

18

0

0

0

0

0

0

 

 

2

PILE NADAPURAM SIDE

27

27

0

0

0

0

0

0

 

 

3

PILE CAP KAINATTY SIDE

6

5

1

1

0

0

1

0

 

 

4

PILE CAP  NADAPURAM SIDE

9

9

0

0

0

0

0

0

 

 

 

PIER KAINATTY  SIDE

6

5

1

1

0

0

1

0

 

 

6

PIER NADAPURAM SIDE

9

8

1

1

0

0

1

0

 

 

7

PIER CAP KAINATTY  SIDE

6

5

1

1

0

0

1

0

 

 

8

PIER CAP NADAPURAM SIDE

9

8

1

1

0

0

1

0

 

 

11

RE/R WALL KAINATTY  SIDE

100%

0%

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

10

RE/R WALL NADAPURAM SIDE

100%

0%

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

12

BEAM/SLAB  Staging Kainatty side

6

4

2

2

0

0

2

0

 

 

13

BEAM/SLAB  Bar bending and Fixing Kainatty side

6

4

2

2

0

0

2

0

 

 

14

BEAM/SLAB  Shuttering  and Concreting  Kainatty side

6

3

3

2

0

0

2

0

 

 

15

BEAM/SLAB  Staging Nadapuram side

9

7

2

1

0

0

1

0

 

 

16

BEAM/SLAB  Bar bending and Fixing Nadapuram side

9

7

2

2

1

0*

1

1

 

P7-P8 girder concrete completed.

17

BEAM/SLAB  Shuttering  and Concreting  Nadapuram side

9

7

2

2

1

0*

1

2

 

P8-P9 girder concrete complete

18

BEAM/SLAB KAINATTY  SIDE

6

3

3

2

1

0

2

0

 

 

19

BEAM/SLAB NADAPURAM SIDE

9

7

2

2

0*

0*

2

1

 

steel work of P7-P8 and P8-P9 slab in progress.

20

HR/FP/KERB KAINATTY  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

21

HR/FP/KERB NADAPURAM SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

22

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

  

 

Availbility of Men

 

 

 

 

 

 

 

Date

05-11=11

06=11=11

11-07-2011

11-08-2011

11-09-2011

11-10-2011

11-11-2011

Nof labours

45

45

45

45

40

40

40 

 

 

Material Stocking Status

Available

 

 

Fine Aggreagate(m3)

10

Cement(bag)

550

Steel(MT)

45

Coarse Aggreagate (m3)

18 

 

Description Progress/Completed Remarks

Pile Concreting (Total no of piles - 45)

completed

 

Pile cap ( Total no. of pile cap 15)

In progress

Done 14 nos.

Pile cap at P4 location

completed

 

Pier concreting ( Total no. of pier  15)

In progress

Done- 13 no

Pier cap( Total no. of pier cap 15)

In progress

Done 14 nos.

Slab concreting

In progress

Done 10 no.

Road work( diversion road)

completed

Nadapuram side.

 RE wall panel casting (total 440)

In progress

Done 200 Nadapuram side, Done 200 Kainatty side

Hand rail casting horizontals

In progress

Done 700 nos.

P8-P9 girder

completed

done concrete.

P7-P8 girder reinforcement

completed

 

P7-P8 girder shuttering

In progress

done concrete.

Excavation for pile cap at P6 location

completed

Done pilecap concrete.

RE wall excavation Nadapuram side

In progress

 

Repair work of diversion road

In progress

  

 

 
Back
 
    
STEELWORK P3-P4.

    
    
RAILWAY ADJ.SPAN STAGING.

    
    
PILECAP STEEL WORK P6

    
    
PILE CAP CONCRETE P6.

    
 
    
DIRT WALL AT AP2

      
 

 

 

 

 

 

 

 

Untitled Document