Works during this week
Service road at anayara sideof ROB ,bentonite pit,etc
Works proposed for next week
Pile-3 no's,service road on Anayara side
Testing of Materials
7 days cube test
Quality of work
Obtained test results are with in the permissible limit for trial cube
Remarks
One telephone junction BOX and 7 telephone post yet to be removed on Anayaraside