   Weekly progress report as on 04.11.2011
    
 

Description

Completed/ Progress

Remarks

ROB at Parappanangady

 

 

Pier cap (Total no of pier Cap- 21)

Completed

19 NOS COMPLETED

RE Wall panel casting ( total 550 nos)

Completed

 

Slab calicut side  (total 10 nos )

In progress

9nos done

slab NH side ( 11 nos)

In progress

10 nos done

P12-P11 staging

completed

 

P12-P11 slab

completed

 

Retaining wall NH side

In progress

Done LHS -90%, RHS- 90%

Dirt wall AP1 concreting

In progress

Done 90%

Handrail casting

In progress

650 nos completed.

Boring at RP1,RP4

pending

design submitted by contractor for pile depth is not approved

NH side RE panel erection

In progress

0.3% completed.

RE wall excavation Calicut side

Completed

 

expansion joint at P18,P19,P17, P16,P15 and P14,p13.

Completed

  

 

 