Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7888475
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 04.11.2011
    
 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

1

PCC for RAFT MOYAN SIDE

3

3

0

0

0

0

0

0

2

PCC for RAFT PALAKKAD SCHOOL SIDE

1

1

0

0

0

0

0

0

3

RAFT PALAKKAD SIDE

1

1

0

0

0

0

0

0

4

RAFT MOYAN SCHOOL SIDE

3

3

0

0

0

0

0

0

5

PIER PALAKKAD SIDE

1

1

0

0

0

0

0

0

6

PIER MOYAN SCHOOL SIDE

3

3

0

0

0

0

0

0

7

PIER CAP PALAKKAD SIDE

1

1

0

0

0

0

0

0

8

PIER CAP MOYAN SCHOOL SIDE

3

3

0

0

0

0

0

0

9

RE/R WALL PALAKKAD  SIDE

100%

75%

25%

0

0.00%

0.00%

0.00%

0.00%

10

RE/R WALL MOYAN SCHOOL SIDE

100%

65%

35%

0

0.00%

0.00%

0.00%

0.00%

11

BEAM/SLAB  Staging Palakad  SIDE

2

2

0

0

0

0

0

0

12

BEAM/SLAB  Bar bending and Fixing Palakad  SIDE

2

2

0

0

0

0

0

0

13

BEAM/SLAB  Shuttering  and Concreting Palakad SIDE

2

2

0

0

0

0

0

o

14

BEAM/SLAB  Staging Moyan schoolSIDE

4

4

0

0

0

0

0

0

15

BEAM/SLAB  Bar bending and Fixing Moyan school SIDE

4

4

0

0

0

0

0

0

16

BEAM/SLAB  Shuttering  and Concreting  Moyan school  SIDE

4

4

0

0

0

0

0

0

17

BEAM/SLAB PALAKKAD  SIDE

2

2

0

0

0

0

0

0

18

BEAM/SLAB MOYAN SCHOOL SIDE

4

4

0

0

0

0

0

0

19

BEAM/SLAB RAILWAY SPAN

7

2.75

4.25

0

0

0

0.5

0.5

20

HR/FP/KERB Pkd  SIDE

100%

30%

70%

0

0.00%

0.00%

0.00%

0.00%

21

HR/FP/KERB Moyen's SIDE

100%

5%

95%

0

0.00%

30.00%

0.00%

5.00%

22

HR/FP/KERB RAILWAY SPAN

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

23

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00% 

 

Description Progress/Completed Remarks
Staging drawing approval from Railways pending 1 no yet to be received (RP3-RP4) 
Fabrication works for railway staging for Bowsrting Completed  
Retaining wall (Palakkad side)  In progress 75% work done
Drain work Retaining wall (Moyan school  side)  In progress done 15%
Retaining wall (Moyan school  side)  In progress 65% done
Bowstring girder In progress Suspenders casting in progress
Handrail fixing & kerb casting In progress 4 slabs of Moyen's side and 2 slabs of Pkd side completed.
Kerb casting In progress Pkd side approach LHS 50 mt done & RHS 35 mt completed
Bowstring girder Stressing and grouting Completed  
RP6-RP7-RP8 railway slab Completed  
RP7-P5, P5-P6, P6-P7, P7-P8 Deck slab and girder completed Moyen's school side deck slabs
P1-P2, P4-RP1 Deck slabs and girder Completed Pkd side deck slabs
RP5-RP6 Barbending and shuttering of girders In progress 2 Nos casting of girder completed
Approach filling In progress Moyen's school side & Pkd side
Cantilver portion of P7-P8 & P1-P2 completed   

 

 
Back
 
    
SUSPENDER CASTING

    
    
RP5-RP6 GIRDER CASTING

    
    
RHS OF BOWSTRING SUSPENDER

    
    
LHS OF BOWSTRING SUSPENDER

    
 
    
GIRDER CASTING

    
    
DESHUTTERED GIRDER OF RP4-RP5

    
    
BOWSTRING SUSPENDER

    
 
 
 

 

 

 

 

 

 

 

Untitled Document