Prevoius Weekly Reports

   Weekly progress report as on 04.11.2011
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE  CALICUT  SIDE 48 47 1 0 2 2 0 4    
2 PILE THIRUR SIDE 24 0 24 0 0 0 0 0    
3 PILE CAP CALICUT  SIDE 12 8 4 0 1 1 0 2    
4 PILE CAP  THIRURSIDE 6 0 6 0 0 0 0 0    
5 PIER CALICUT SIDE 12 3 9 0 1 1 0 0   p10 two lifts completed
6 PIER THIRUR SIDE 6 0 6 0 0 0 0 0    
7 PIER CAPCALICUT   SIDE 12 0 12 0 0 0 0 0   staging @ p8 completed
8 PIER CAP THIRUR SIDE 6 0 6 0 0 0 0 0    
9 RE/R WALL CALICUT   SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
10 RE/R WALLTHIRUR SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
11 BEAM/SLAB CALICUT   SIDE 12 0 12 0 0 0 0 0    
12 BEAM/SLAB THIRUR SIDE 6 0 6 0 0 0 0 0    
13 HR/FP/KERB CALICUT   SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
14 HR/FP/KERBTHIRUR SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%     

 

Availbility of Men           
Date 28-10-2011 29-10-2011 01-11-2011 02-11-2011 03-10-2011 04-11-2011
Nof labours 30 30 35 30 30 35 

 

Utility shifting  
Utilities to be shifted Status
BSNL shifting in progress
KSEB shifting in progress
KWA shifting in progress 

 

 
Back
 
    
PILE CONCRETE @ A1

    
    
PILE BREAKING @ P1

    
    
EW EXCAVATION @ P1

      
 

 

 

 

 

 

 

 