Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8053957
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 04.11.2011
    
 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

Remarks

1

PILE THRIKKARIPUR  SIDE

33

33

0

0

0

0

0

0

 

2

PILE EZHIMALA SIDE

27

27

0

0

0

0

0

0

 

3

PILE PAYYANNUR SIDE

27

27

0

0

0

0

0

0

 

4

PILE CAP THRIKKARIPUR  SIDE

11

11

0

0

0

0

0

0

 

5

PILE CAP EZHIMALA SIDE

9

9

0

0

0

0

0

0

 

6

PILE CAP PAYYANNUR SIDE

9

9

0

0

0

0

0

0

 

9

PIER THRIKKARIPUR  SIDE

11

11

0

0

0

0

0

0

 

8

PIER EZHIMALA SIDE

9

9

0

0

0

0

0

0

 

9

PIER PAYYANNUR SIDE

9

9

0

0

0

0

0

0

 

10

PIER CAP THRIKKARIPUR  SIDE

11

11

0

0

0

0

0

0

 

11

PIER CAP EZHIMALA SIDE

9

9

0

0

0

0

0

0

 

12

PIER CAP PAYYANNUR SIDE

9

9

0

0

0

0

0

0

 

16

RE/R WALL THRIKKARIPUR  SIDE

100%

65%

35%

0

10.00%

10.00%

5.00%

10.00%

 

17

RE/R WALL EZHIMALA SIDE

100%

55%

45%

0

5.00%

5.00%

0.00%

5.00%

 

18

RE/R WALL PAYYANNUR SIDE

100%

10

90%

0

0.00%

0.00%

0.00%

0.00%

 

19

BEAM/SLAB  Staging Thrikkaripur side

10

10

0

0

0

0

0

0

 

20

BEAM/SLAB  Bar bending and Fixing Thrikkaripur side

10

10

0

0

0

0

0

0

 

21

BEAM/SLAB  Shuttering  and Concreting  Thrikkaripur side

10

10

0

0

0

0

0

0

 

22

BEAM/SLAB  Staging Ezhimala side

7

7

0

0

0

0

0

0

 

23

BEAM/SLAB  Bar bending and Fixing Ezhimala side

7

7

0

0

0

0

0

0

 

24

BEAM/SLAB  Shuttering  and Concreting  Ezhimala side

7

7

0

0

0

0

0

0

 

25

BEAM/SLAB  Staging Payyanur side

10

8

2

2

0

0

2

0

 

26

BEAM/SLAB  Bar bending and Fixing Payyanur side

10

8

2

2

0

0

2

0

 

27

BEAM/SLAB  Shuttering  and Concreting Payyanur side

10

8

2

2

0

0

2

0

 

28

BEAM/SLAB THRIKKARIPUR  SIDE

10

10

0

0

0

0

0

0

 

29

BEAM/SLAB EZHIMALA SIDE

7

7

0

0

0

0

0

0

 

30

BEAM/SLAB PAYYANNUR SIDE

10

8

2

1

0

0

2

0

 

31

HR/FP/KERB THRIKKARIPUR  SIDE

100%

0

100%

30%

0.00%

0.00%

0.00%

30.00%

 

32

HR/FP/KERB EZHIMALA SIDE

100%

30%

70%

30%

10.00%

0.00%

0.00%

0.00%

 

33

HR/FP/KERB PAYYANNUR SIDE

100%

100%

0%

0

40.00%

40.00%

0.00%

0.00%

 

34

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

  

 

Availbility of Men               
Date 29-10-2011 30-10-2011 31-10-2011 01-11-2011 02-11-2011 03-11-2011 04-11-2011
Nof labours 45 40 45 45 30 40 45 

 

Material Stocking Status Required Available
Coarse Aggreagate (m3) available  
Fine Aggreagate(m3) available  
Cement(bag) 200 400
Steel(MT) 3 30 

 

Utility shifting  
Utilities to be shifted Status
BSNL completed
KSEB completed
KWA completed
Others completed 

 

PROGRESS OF WORK UPTO 28-10-11

ROB at Payyannur

 

 

Pier cap concreting (Total no of pier cap- 29)

completed

 

Slab  Thrikkaripur side (  10 nos)

completed

10 nos done

Slab Ezhimala side ( 7 nos)

completed

7nos done

Slab Payyanur side ( 10 nos)

In progress

8 nos done

 Retaining wall/RE wall panel casting- Ezhimala side

In progress

done 55%

Retaining wall Thrikkaripur side (RHS)

In progress

Done 70%

Handrail & Kerb payyannur side

completed

 

Expansion joint: Payyannur side

completed

 

Expansion joint: Ezhimala side

In progress

2 locations- P11,P12 complete

Expansion joint: Thrikkarippur side

 

5 span planned tkis week

Kerb

In progress

(total 20 spans complete) 

 

 
Back
 
    
RAILWAY PORTION VIEW FROM P17

    
    
PAYYANNUR SIDE APPROACH PORTION 1

    
    
HANDRAIL PORTION PAYYANNUR SIDE 1

    
    
APPROACH PORTION VIEW FROM AP3

    
 
 
 

 

 

 

 

 

 

 

Untitled Document