Si No
|
Activity Description
|
Total Quantity
|
Cumulative progress upto last week
|
Balance work up to last week
|
Cumulative delay in Qty up to last week
|
Work planned during the week
|
Actual work done during the week
|
Cumulative delay in Qty up to this week
|
Work Planned for next week
|
Remarks
|
1
|
PILE THRIKKARIPUR SIDE
|
33
|
33
|
0
|
0
|
0
|
0
|
0
|
0
|
|
2
|
PILE EZHIMALA SIDE
|
27
|
27
|
0
|
0
|
0
|
0
|
0
|
0
|
|
3
|
PILE PAYYANNUR SIDE
|
27
|
27
|
0
|
0
|
0
|
0
|
0
|
0
|
|
4
|
PILE CAP THRIKKARIPUR SIDE
|
11
|
11
|
0
|
0
|
0
|
0
|
0
|
0
|
|
5
|
PILE CAP EZHIMALA SIDE
|
9
|
9
|
0
|
0
|
0
|
0
|
0
|
0
|
|
6
|
PILE CAP PAYYANNUR SIDE
|
9
|
9
|
0
|
0
|
0
|
0
|
0
|
0
|
|
9
|
PIER THRIKKARIPUR SIDE
|
11
|
11
|
0
|
0
|
0
|
0
|
0
|
0
|
|
8
|
PIER EZHIMALA SIDE
|
9
|
9
|
0
|
0
|
0
|
0
|
0
|
0
|
|
9
|
PIER PAYYANNUR SIDE
|
9
|
9
|
0
|
0
|
0
|
0
|
0
|
0
|
|
10
|
PIER CAP THRIKKARIPUR SIDE
|
11
|
11
|
0
|
0
|
0
|
0
|
0
|
0
|
|
11
|
PIER CAP EZHIMALA SIDE
|
9
|
9
|
0
|
0
|
0
|
0
|
0
|
0
|
|
12
|
PIER CAP PAYYANNUR SIDE
|
9
|
9
|
0
|
0
|
0
|
0
|
0
|
0
|
|
16
|
RE/R WALL THRIKKARIPUR SIDE
|
100%
|
65%
|
35%
|
0
|
10.00%
|
10.00%
|
5.00%
|
10.00%
|
|
17
|
RE/R WALL EZHIMALA SIDE
|
100%
|
55%
|
45%
|
0
|
5.00%
|
5.00%
|
0.00%
|
5.00%
|
|
18
|
RE/R WALL PAYYANNUR SIDE
|
100%
|
10
|
90%
|
0
|
0.00%
|
0.00%
|
0.00%
|
0.00%
|
|
19
|
BEAM/SLAB Staging Thrikkaripur side
|
10
|
10
|
0
|
0
|
0
|
0
|
0
|
0
|
|
20
|
BEAM/SLAB Bar bending and Fixing Thrikkaripur side
|
10
|
10
|
0
|
0
|
0
|
0
|
0
|
0
|
|
21
|
BEAM/SLAB Shuttering and Concreting Thrikkaripur side
|
10
|
10
|
0
|
0
|
0
|
0
|
0
|
0
|
|
22
|
BEAM/SLAB Staging Ezhimala side
|
7
|
7
|
0
|
0
|
0
|
0
|
0
|
0
|
|
23
|
BEAM/SLAB Bar bending and Fixing Ezhimala side
|
7
|
7
|
0
|
0
|
0
|
0
|
0
|
0
|
|
24
|
BEAM/SLAB Shuttering and Concreting Ezhimala side
|
7
|
7
|
0
|
0
|
0
|
0
|
0
|
0
|
|
25
|
BEAM/SLAB Staging Payyanur side
|
10
|
8
|
2
|
2
|
0
|
0
|
2
|
0
|
|
26
|
BEAM/SLAB Bar bending and Fixing Payyanur side
|
10
|
8
|
2
|
2
|
0
|
0
|
2
|
0
|
|
27
|
BEAM/SLAB Shuttering and Concreting Payyanur side
|
10
|
8
|
2
|
2
|
0
|
0
|
2
|
0
|
|
28
|
BEAM/SLAB THRIKKARIPUR SIDE
|
10
|
10
|
0
|
0
|
0
|
0
|
0
|
0
|
|
29
|
BEAM/SLAB EZHIMALA SIDE
|
7
|
7
|
0
|
0
|
0
|
0
|
0
|
0
|
|
30
|
BEAM/SLAB PAYYANNUR SIDE
|
10
|
8
|
2
|
1
|
0
|
0
|
2
|
0
|
|
31
|
HR/FP/KERB THRIKKARIPUR SIDE
|
100%
|
0
|
100%
|
30%
|
0.00%
|
0.00%
|
0.00%
|
30.00%
|
|
32
|
HR/FP/KERB EZHIMALA SIDE
|
100%
|
30%
|
70%
|
30%
|
10.00%
|
0.00%
|
0.00%
|
0.00%
|
|
33
|
HR/FP/KERB PAYYANNUR SIDE
|
100%
|
100%
|
0%
|
0
|
40.00%
|
40.00%
|
0.00%
|
0.00%
|
|
34
|
BC/PAINTING
|
100%
|
0
|
100%
|
0
|
0.00%
|
0.00%
|
0.00%
|
0.00%
|
|