Prevoius Weekly Reports

   Weekly progress report as on 04.11.2011
    
 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

1

PILE KAINATTY  SIDE

18

18

0

0

0

0

0

0

 

 

2

PILE NADAPURAM SIDE

27

27

0

0

0

0

0

0

 

 

3

PILE CAP KAINATTY SIDE

6

5

1

1

0

0

1

0

 

 

4

PILE CAP  NADAPURAM SIDE

9

9

0

0

0

0

0

0

 

 

 

PIER KAINATTY  SIDE

6

5

1

1

0

0

1

0

 

 

6

PIER NADAPURAM SIDE

9

8

1

1

0

0

1

0

 

 

7

PIER CAP KAINATTY  SIDE

6

4

2

1

0

1

1

0

 

P4 pier cap complete

8

PIER CAP NADAPURAM SIDE

9

8

1

1

0

0

1

0

 

 

11

RE/R WALL KAINATTY  SIDE

100%

0%

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

10

RE/R WALL NADAPURAM SIDE

100%

0%

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

12

BEAM/SLAB  Staging Kainatty side

6

3

3

3

0

0*

2

1

 

P3-P4 girder staging work in progress

13

BEAM/SLAB  Bar bending and Fixing Kainatty side

6

3

3

3

0

0

3

1

 

 

14

BEAM/SLAB  Shuttering  and Concreting  Kainatty side

6

3

3

2

0

0

2

0*

 

P3-P4 girder concrete planned

15

BEAM/SLAB  Staging Nadapuram side

9

7

2

1

0

0

1

0

 

 

16

BEAM/SLAB  Bar bending and Fixing Nadapuram side

9

7

2

2

0

0

2

0

 

 

17

BEAM/SLAB  Shuttering  and Concreting  Nadapuram side

9

7

2

2

0

0

1

0

 

 

18

BEAM/SLAB KAINATTY  SIDE

6

3

3

2

0

0

2

0

 

 

19

BEAM/SLAB NADAPURAM SIDE

9

7

2

2

0

0

1

0

 

 

20

HR/FP/KERB KAINATTY  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

21

HR/FP/KERB NADAPURAM SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

22

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

  

 

 

Availbility of Men

 

 

 

 

 

 

 

Date

29-10-2011

30-10-2011

31-10-2011

01-11-2011

02-11-2011

03-11-2011

04-11-2011

Nof labours

82

82

82

82

82

82

82 

 

 

PROGRESS OF WORK UPTO 04-11-11

 

Description

 Progress/Completed

Remarks 

 

Pile Concreting (Total no of piles - 45)

completed

 

 

Pile cap ( Total no. of pile cap 15)

In progress

Done 14 nos.

 

Pile cap at P4 location

completed

 

 

Pier concreting ( Total no. of pier  15)

In progress

Done- 13 no

 

Pier cap( Total no. of pier cap 15)

In progress

Done 13 nos,P4complete this week.

 

Slab concreting

In progress

Done 10 nos

 

Road work( diversion road)

completed

 

 

 RE wall panel casting (total 440)

In progress

Done 200 Nadapuram side, Done 200 Kainatty side

 

Hand rail casting horizontals

In progress

Done 520 nos

 

Excavation for pile cap at P5 location

completed

 

 

RE wall excavation Nadapuram side

In progress

 

 

Repair work of diversion road

In progress

  

 
Back
 
    
STAGING DONE FOR P3-P4 GIRDERS

    
    
P4 PIERCAP PEDESTAL CONCRETING DONE

    
    
P4 PIERCAP CONCRETING DONE

    
    
DIRT WALL READY FOR CONCRETE

    
 
 
 

 

 

 

 

 

 

 