Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7887777
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 04.11.2011
    
 

SlNo

Activity –which can be completed without caution

Description

Total Quantity

Cumulative progress up to this week

(1)

Balance  work

(2)

Cumulative delay in weeks after

Spplagmnt

(3)

Work  planned  during the week

(4)

Actual work done during the last week

(5)

Short fall in the last week 

(6)

Work 

Planned for next week

(7)

No of days remaining for completion as per the weekly plan

1

Re wall towards NH side

100%

34

66

32

 

 

0

0

 0

3

Approach

 Span

 

5

 

5

0

37

-

-

-

-

 

4

Pier cap

2

2

0

46

 0

 0

 0

 0

 0

5

Pile (Rly)pulikakadavuside

4

 

4

0

60

 0

 0

0

6

Pile (Rly)Nhside

4

4

0

60

0

0

0

0

0

6

Piers (Rly)

 

2

2

0

51

 0

 0

 0

 0

 

9

R0AD WORK

{WBM} towards pulikkakadavuside

100%

90

 

0

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1O

Kerb/handrail  (approach portion)N.H side

200m

Inner kerbconcreting complete for a distance of  25 metres.Handrailposts  concreted for a. distance of 50 metres.Nowork in the last week.

 

Nil

 

 

 

 

 

12

Friction slab  approach portion(N.H side

200m

 

No work in the last week

 

 

 

 

     

 

 

 

Material Stocking Status

 

 

 

 

Coarse Aggreagate (m3)

8

9

Remarks

 

Fine Aggreagate(m3)

 5

 8

 .

 

Cement(bag)

 9

 12

 

 

Steel(MT)

 6

5

 

 

 RE blocks

 2150 available at site

 

 

  

 

 

Utility shifting

 

 

 

 

Utilities to be shifted

Status

Remarks

 

 

BSNL

 

 

 

 

KSEB

 nohindrance

 

 

 

KWA

 

 .

 

 

Others

 

No hindrance

 

 

  

 

 Climate & Labour Details

DATE

29-10-2011

30-10-2011

31-10-2011

1-11-2011

2-11-2011

3-11-2011

4-11-2011

Weather

cloudy

rainy

Rainy

Rainy

Rainy

Rainy

Sunny 

Labour 10 1 1 1 1 1 1

 

 Daily Activity Report

Sl.

No

Date

Activity

1

29-10-2011

Pile chipping work completdat the P8 location

2

31-10-2011

 

No work due to heavy rain

 

3

1-11-2011

No laboursat the site .So no work possible

4

2-11-2011

No laboursat the site .So no work possible

 

 

 

5

 

6

  

 

 

 

3-11-2011

 

4-11-2011

 

 

No laboursat the site .So no work possible

 

Cleaning up of the location P8 for pile cap reinforcement

 

 

 

•Concreting of the Pile  P8(5) , P8(3),P8(2),P8(1),P8(4) completed.
•Heavy rain affecting the progress of work
•Concreting of  pile cap at P8 planned for the next week.
•Pile chipping work completed at P8 location
•Caution not yet obtained to start piling work at P7 location 
 
Back
 
    
WTAER LOGGED DUE TO HEAVY RAIN

    
    
PILE CHIPPING AT P8 (2)

    
    
PILE CHIPPING AT P8 (2)

    
    
PILE CAP EXCAVATION AND CHIPPING COMPLETE

    
 
    
P8 PILE CAP LOCATION

    
    
CLEANING UP OF SURFACE AT P8 LOCATION FOR PILE CAP

      
 

 

 

 

 

 

 

 

Untitled Document