   Weekly progress report as on 04.11.2011
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE SHORNUR  SIDE 9 9       Completed      
2 PILE M.C SIDE 36 36       Completed        
3 PILE CAP SHORNUR SIDE 3 3       Completed        
4 PILE CAP  M.C SIDE 12 12       Completed        
5 PIER SHORNUR  SIDE 3 3       Completed        
6 PIER M.C SIDE 12 12       Completed        
7 PIER CAP SHORNUR  SIDE 3 3       Completed        
8 PIER CAP M.C SIDE 12 12       Completed        
9 RE/R WALL SHORNUR SIDE 100% 39 61% 0 10.00% 10.00% 63.00% 10.00% 0 RCC wall first lift concreting completed on one side.i.e (32 metres ).Excavation on the other side is planned for next week.
10 RE/R WALL M.C SIDE 100% 9 91% 0 5.00% 0.00% 13.00% 5.00% 0 No work has been possible in the RE wall portion due to heavy rain throughout the week.Due to heavy rain at the site ,it is impossible to do the rolling work before laying PCC
11 BEAM/SLAB SHORNUR  SIDE 3 2 1 0 0 0 0 0 0  
12 BEAM/SLAB M.C SIDE 12 11 1 0 1 1 0 0 0 deshuttering of the span P5-P4 in progress.Work is very slow due to lack of labour.
13 HR/FP/KERB SHORNUR  SIDE 100% 50 50% 0 0.00% 0.00% 0.00% 0.00% 0 days  
14 HR/FP/KERB M.C SIDE 100% 53 47% 0 8.00% 1.00% 6.00% 8.00%   Iinner kerb shuttering and reinforcement work in progress at the span P7-P8
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%     

 

 

Availbility of Men 

             
Date 29-10-2011 30-10-2011 31-10-2011 11-01-2011 11-02-2011 11-03-2011 11-04-2011
Nof labours 9 9 9 9 9 9

 

 

Material Stocking Status

         
  Required Available Remarks    
Fine aggregate {cft} 300 300      
Cement(bag) 300 126 stock will be replendished soon    
Steel inT 11 12      
Coarse Aggreagate (cft) 300 200      

 

Utility shifting  
Utilities to be shifted  
BSNL COMPLETED
KSEB COMPLETED
KWA COMPLETED
Others COMPLETED 

 

 