   Weekly progress report as on 04.11.2011
    

 

Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE Muthambi side 27 18 9 0 0 0 0      
2 PILE Thamarassery side 33 6 27 0 6 5 0 6    
3 PILE NH SIDE 30 3 30 0 4 3 0 4    
4 PILE CAP Muthambi SIDE 9 0 9 0 2 0 0 2   P15,P14,P13 pile cap excavation complete
4 PILE CAP Thamarassery SIDE 11 0 11 0 0 0 0 0    
5 PILE CAP NH SIDE 10 0 10 0 0 0 0 0    
6 PIER Muthambi  SIDE 9 0 9 0 0 0 0 0    
7 PIER Thamarassery SIDE 11 0 11 0 0 0 0 0    
8 PIER NH SIDE 10 0 10 0 0 0 0 0    
9 PIER CAP Muthambi  SIDE 9 0 9 0 0 0 0 0    
10 PIER CAP Thamarassery SIDE 11 0 11 0 0 0 0 0    
11 PIER CAP NH SIDE 10 0 10 0 0 0 0 0    
12 RE/R WALL Muthambi side 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
13 RE/R WALL Thamarassery side SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
14 RE/R WALL NH SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
15 BEAM/SLAB Muthambi SIDE 8 0 8 0 0 0 0 0    
16 BEAM/SLAB Thamarassery SIDE 10 0 10 0 0 0 0 0    
17 BEAM/SLABNH SIDE 10 0 10 0 0 0 0 0    
18 HR/FP/KERB Muthambi SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
19 HR/FP/KERB thamarassery SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
20 HR/FP/KERB NH SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
21 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
22 Deck Slab                    
23 Utility shifting                   KSEB estimate 1st part complete. Executive engineer sanctioned estimate 

 

 

Availbility of Men 

             
Date 29/10/2011 30/10/2011 31/10/2011 11-01-2011 11-02-2011 11-03-2011 11-04-2011
Nof labours 32 32 32 35 35 35 35 

 

 

Material Stocking Status

 

Required

 

Available

Coarse Aggreagate (m3) 100 120
Fine Aggreagate(m3) 100 120
Cement(bag) 1000 900
Steel(MT) 18 27 

 

Progress of ROB's

 

Pile concreting In progress Done 27 nos
Pile cap excavation for P13,P14,P15 Completed  
Site level survey completed  
7 day Cube test Completed  
28th day Cube test Completed  
BSNL, KWA site inspection for utility shifting In progress  
KSEB site inspection for utility shifting completed  
KSEB utilities estimate 1st part Completed  Executive engineer sanctioned estimate
site clearing in thamarassery area In progress  
filling work towards thamarassery side In progress 100 % complete
site clearing towards NH side In progress filling 80% completed
filling work in piling location Completed upto AP2 area 
 
Back
 
    
PILEAP1B BORING

    
    
PILE P27C CONCRETING

    
    
PILE P26B BORING

    
    
PILE 26C CONCRETING

    
 
    
CHIPPING FOR PILES P15

      
 

 

 

 

 

 

 

 