   Weekly progress report as on 28.10.2011
    

 

Description

Progress/Completed 

Remarks 

Pier cap (Total no of pier Cap- 21)

Completed

 

RE Wall panel casting ( total 550 nos)

Completed

 

Slab calicut side  (total 10 nos )

In progress

9nos done

slab NH side ( 11 nos)

In progress

10nos done

P12-P11 staging

completed

 

P12-P11 girder reinforcement and shuttering

Completed

slab completed

Retaining wall NH side

In progress

Done LHS -90%, RHS- 90%

Dirt wall AP1 concreting

In progress

Done 90%

Handrail casting

In progress

700nos

Boring at RP1

pending

piling is pending.(rock boared up to 80 cm.)

NH side RE panel erection

In progress

30% completed

RE wall excavation Calicut side

Completed

 

expansion joint at P18,P19,P17, P16,P15 P14,p13

Completed

7 noscompleted. 

 

 
Back
 
    
SLAB CONCRETING-P11-P12.

    
    
RE WALL WORKS.

    
    
RAILWAY PORTION.

    
    
KERB CONCRETING.

    
 
    
AP2-SIDE SLAB COMPLETED.

      
 

 

 

 

 

 

 

 