Description
|
Progress/Completed
|
Remarks
|
Pier cap (Total no of pier Cap- 21)
|
Completed
|
|
RE Wall panel casting ( total 550 nos)
|
Completed
|
|
Slab calicut side (total 10 nos )
|
In progress
|
9nos done
|
slab NH side ( 11 nos)
|
In progress
|
10nos done
|
P12-P11 staging
|
completed
|
|
P12-P11 girder reinforcement and shuttering
|
Completed
|
slab completed
|
Retaining wall NH side
|
In progress
|
Done LHS -90%, RHS- 90%
|
Dirt wall AP1 concreting
|
In progress
|
Done 90%
|
Handrail casting
|
In progress
|
700nos
|
Boring at RP1
|
pending
|
piling is pending.(rock boared up to 80 cm.)
|
NH side RE panel erection
|
In progress
|
30% completed
|
RE wall excavation Calicut side
|
Completed
|
|
expansion joint at P18,P19,P17, P16,P15 P14,p13
|
Completed
|
7 noscompleted.
|