Works during this week
|
Pilecaps, Piers and piles in progress, pier hieght shall be done @ P11
|
Works proposed for next week
|
piles at P12 and A1, pier hieghts at P11,P10 and pile cap @ p9,P3
|
Testing of Materials
|
Done and records maintained at site
|
Quality of work
|
Satisfactory
|
Remarks
|
work slow due to lacof labours for piling
|
|
Description |
Progress/Completed |
Remarks |
Initial Pile Load Test
|
Completed
|
|
Pile
|
In progress
|
Done 44 nos
|
earthwork excavation for pile cap
|
Completed
|
at 5 locations
|
pile cap PCC
|
completed
|
at P5,P6,P7,P8
|
P8 pile cap
|
Completed
|
|
Pile cap
|
in progress
|
P7,P6,P5,P9 complete this week
|
Pier
|
in progress
|
P7.P8,P11 completed
|
|