Prevoius Weekly Reports

   Weekly progress report as on 28.10.2011
    

 

Revised Progress Report For Mulankunnathukavu ROB for the week ending on 28-10-2011

 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

1

PILE SHORNUR  SIDE

9

9

 

 

 

Completed

 

 

 

2

PILE M.C SIDE

36

36

 

 

 

Completed

 

 

 

 

3

PILE CAP SHORNUR SIDE

3

3

 

 

 

Completed

 

 

 

 

4

PILE CAP  M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

5

PIER SHORNUR  SIDE

3

3

 

 

 

Completed

 

 

 

 

6

PIER M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

7

PIER CAP SHORNUR  SIDE

3

3

 

 

 

Completed

 

 

 

 

8

PIER CAP M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

9

RE/R WALL SHORNUR SIDE

100%

39

61%

0

10.00%

2.00%

63.00%

10.00%

0

RCC wall concreting completed for a distance of 7 more metres.The work in the RCC retaining wall is very slow due to lack of labour.

10

RE/R WALL M.C SIDE

100%

9

91%

0

15.00%

0.00%

13.00%

5.00%

0

No work has been possible in the RE wall portion due to heavy rain throughout the week.Heavy rain has resulted in water logging and therefore no work is possible.

11

BEAM/SLAB SHORNUR  SIDE

3

2

1

0

0

0

0

0

0

 

12

BEAM/SLAB M.C SIDE

12

11

1

0

1

1

0

0

0

deshuttering of the span P5-P4 in progress.Work is very slow due to lack of labour.

13

HR/FP/KERB SHORNUR  SIDE

100%

50

50%

0

0.00%

0.00%

0.00%

0.00%

0 days

 

14

HR/FP/KERB M.C SIDE

100%

53

47%

0

8.00%

1.00%

6.00%

8.00%

 

Miscellaneous works in progress.Handrail fixing is completed for P3-P4,inner kerb concreting completed at P3-P4inner kerb reinforcement in progress at P8-P7,expansion joint concreting completed at P5.footpath slab concreting completed at AP2-P13 span.

15

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

 

Availbility of Men

 

 

 

 

 

 

 

Date

22-10-2011

23-10-2011

24-10-2011

25-10-2011

26-10-2011

27-10-2011

28-10-2011

Nof labours

7

7

7

7

7

7

7

 

Material Stocking Status

 

 

 

Required

Available

Fine aggregate {cft}

300

300

Cement(bag)

300

200

Steel inT

5

9

Coarse Aggreagate (cft)

300

340

 

Utility shifting

 

Utilities to be shifted

 

BSNL

COMPLETED

KSEB

COMPLETED

KWA

COMPLETED

Others

COMPLETED

 