Prevoius Weekly Reports

   Weekly progress report as on 28.10.2011
    
 

Si No

Activity Description

Total Quantity

Cumulative progress upto 27.10.11

Balance  work up to 27.10.11

Cumulative delay in Qty up to 27.10.11

Work  planned  during the week

Actual work done during the week

delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

1

PILE  Palarivattom side(Approach portion)

31

28

3

0

0

0

0

0

kwa line to be shifted

2

PILE Palarivattom side(railway portion)

6

0

6

0

0

0

0

0

"      "

3

PILE vytilla side(Approach portion)

42

0

42

0

0

0

0

0

"      "

4

PILE vytilla side(railway portion)

6

0

6

0

0

0

0

0

"      "

5

PILE CAP Palarivattom side(Approach portion)

8

7

1

1

1

1

0

0

"      "

6

PILE CAP Palarivattomside(railway portion)

1

0

1

0

0

0

0

0

"      "

7

PILE CAP vytilla side(Approach portion)

9

0

9

0

0

0

0

0

"      "

8

PILE CAP vytilla side(railway portion)

1

0

1

0

0

0

0

0

"      "

9

PIER Palarivattom side(Approach portion)

8

7

1

0

3

1

0

0

 

10

PIER Palarivattomside(railway portion)

1

0

1

0

0

0

0

0

 

11

PIER Vytilla side(Approach portion)

9

0

9

0

0

0

0

0

"      "

12

PIER vytilla side(railway portion)

1

0

1

0

0

0

0

0

"      "

13

PIER  CAP Palarivattom side(Approach portion)

8

7

1

0

0

0

2

2

 

14

PIER CAP Palarivattomside(railway portion)

1

0

1

0

0

0

0

0

 

15

PIER CAP  Vytilla side(Approach portion)

9

0

9

0

0

0

0

0

"      "

16

PIER CAP vytilla side(railway portion)

1

0

1

0

0

0

0

0

"      "

17

RE WALL PANEL

355

355

0

0

0

1

0

0

 

WORKS AT SITE

GIRDER

 
A2 P15-  End shutter placing in progress.
P15 P14-Sheathing pipe fixing  
P14 P13-Staging Work in progress  

 

Labour Report              
               
Date 21.10.11 22.10.11 23.10.11 24.10.11 25.10.11 26.10.11 27.10.11
Day Fri Sat Sun Mon Tue Wed Thurs
Climate sunny sunny sunny sunny sunny & rainy sunny & rainy sunny & rainy
No.of labours 21 30 12 30 25 18 21 

 

Availability of Material     
Materials Required for week ending on 02.11.11 Available as on 28.09.2011
Fine aggregate(M3) Ready Mix Concrete
Coarse aggregate(M3)
Cement(BAG)
Steel(TONN) 2 45 

 

Pile Concreting  in progress Done 28 nos
Pile cap In progress Done 7 nos
Pier concreting In progress Done 7 nos 
Pier cap  In progress Done 7 nos, 
P15,AP2 pedestal concrete  completed  
staging for P15-AP2 girder Completed  
AP2-P15 girder reinforcement Completed  
P15-P14 girder staging Completed  
P15-P14 girder reinforcement In progress  
P14-P13 girder shuttering In progress  
Electricity line shifting for P9 location completed  
Railway trees cut near P11, RP1 completed Location cleared for piling
KWA lines shifting towards Vyttila side In progress Work resumed on 25.10.11
KSEB 2 overhead line shifting completed  
KSEB utility shifting    KSEB post shifting in progress
Pile P9 KWA line shifting pending water supply line to railway broke    at 07-05-2011 
Pile load test P14, P4 completed  
RE Wall panel casting (355nos) completed done 355nos
Shifting of railway signal cable at RP1 commenced Resumed on 17.10.11and in progress
Pedestal P11 completed  
     

 

 
Back
 
    
SIGN BOARD

    
    
RLY CABLES RELAYING

    
    
P 11 PEDESTAL CONCRETING

    
    
KSEB METER SHIFTING

    
 
    
JOINT INSPECTION KWA & KRL

    
    
DISMANTLING RLY. HEIGHT GUAGE

    
    
A2 P15 SHUTTERING

    
 
 
 

 

 

 

 

 

 

 