Prevoius Weekly Reports
|
23.01.2010 |
|
ROB at Athani
Work Planned upto 23.01.2010 |
Completed/Progress |
Delay |
RE wall works Medical College side |
Started |
Delay by the contractor |
Fixing of panels |
In progress |
|
Retaining wall on Shornur side |
In progress |
|
Approach slab |
Completed |
|
Friction slab |
Started |
|
|
|
Back |
|
No images are uploaded for this Weekly Reports
|
|
|