Description |
Progress/Completed |
Remarks |
|
Pier cap (Total no of pier Cap- 21) |
Completed |
|
|
RE Wall panel casting ( total 550 nos) |
Completed |
|
|
Slab calicut side (total 10 nos ) |
In progress |
9nos done |
|
slab NH side ( 11 nos) |
In progress |
10nos done |
|
P12-P11 staging |
completed |
|
|
P12-P11 girder reinforcement and shuttering |
Completed |
slab completed |
|
Retaining wall NH side |
In progress |
Done LHS -90%, RHS- 90% |
|
Dirt wall AP1 concreting |
In progress |
Done 90% |
|
Handrail casting |
In progress |
500 nos complete |
|
Boring at RP1 |
pending |
piling in progress |
|
NH side RE panel erection |
In progress |
|
|
RE wall excavation Calicut side |
Completed |
|
|
expansion joint at P18,P19,P17, P16,P15 and P14 |
Completed |
|