   Weekly progress report as on 21.10.2011
    

 

Description Progress/Completed  Remarks 
Pier cap (Total no of pier Cap- 21) Completed  
RE Wall panel casting ( total 550 nos) Completed  
Slab calicut side  (total 10 nos ) In progress 9nos done
slab NH side ( 11 nos) In progress 10nos done
P12-P11 staging  completed  
P12-P11 girder reinforcement and shuttering Completed slab completed
Retaining wall NH side In progress Done LHS -90%, RHS- 90%
Dirt wall AP1 concreting  In progress Done 90%
Handrail casting In progress 500 nos complete
Boring at RP1 pending piling in progress
NH side RE panel erection In progress  
RE wall excavation Calicut side Completed  
expansion joint at P18,P19,P17, P16,P15 and P14 Completed  
 
Back
 
    
RAIWAY STAFFS AT SITE.

    
    
PILING RP1.

    
    
P11-P12 SLAB WORK.

    
    
P11-P12 GIRDER SHUTTERING.

    
 
    
GIRDER CONCRETING P11-P12.

      
 

 

 

 

 

 

 

 