   Weekly progress report as on 21.10.2011
    
 
Description Progress/Completed Remarks

Pile Concreting (44 nos)

completed

Done 44 nos

Pile cap

In progress

done 9 nos

Pier

In progress

done 7 nos

Pier cap

In progress

done 3 no

Aburtment stub column at A1

completed

 

Pier P1 bottom honge

completed

 

Retaining wall puliyanam side

In progress

15m third lift complete

Dirt wall work

In progress

 

Extension of culvert slab over irrigation canal

completed

 

Drain work NH side

In progress

15 m complete

KSEB overhead electric line shifting NH side

completed

 

Utilities (KWA) in Puliyanam side

completed

 

Cutting, bending and placing of reinforcement for Base slab and side wall of drain

completed

 

 Excavation for drain 15m . (NH Side)

completed

 

PCC for drain 30.0m . (NH side )

completed

 

 Base slab of drain 35m  (Puliyanam side)

completed

  

 

 
Back
 
    
RC WALL SHUTTERING-PULIYNAM SIDE

    
    
RC WALL PULIYANAM SIDE-EXCAVATION

    
    
PILE CAP P6 EXCAVATION COMPLETED

    
    
PIER P2 TOP HAUNCH CONCRETE

    
 
    
PIER P2 1ST LIFT CONCRETE

    
    
PIER CAP P9 CONCRETE

      
 

 

 

 

 

 

 

 