1
Works during this week
Pilecaps, Piers and piles in progress, pier hieght shall be done @ P7
2
Works proposed for next week
piles at P12 and A1, pier hieghts at P7,P6 and pile cap @ p11,P10
3
Testing of Materials
Done and records maintained at site
4
Quality of work
Satisfactory
Remarks
work slow due to lacof labours for piling