   Weekly progress report as on 21.10.2011
    
 

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

PILE KAINATTY  SIDE

18

18

0

0

0

0

0

0

 

 

PILE NADAPURAM SIDE

27

27

0

0

0

0

0

0

 

 

PILE CAP KAINATTY SIDE

6

5

1

1

0

0

1

0

 

 

PILE CAP  NADAPURAM SIDE

9

9

0

0

0

0

0

0

 

 

PIER KAINATTY  SIDE

6

5

1

1

0

0

1

0

 

 

PIER NADAPURAM SIDE

9

8

1

1

0

0

1

0

 

 

PIER CAP KAINATTY  SIDE

6

4

2

2

0

0

2

0

 

 

PIER CAP NADAPURAM SIDE

9

8

1

1

0

0

1

0

 

 

RE/R WALL KAINATTY  SIDE

100%

0%

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

RE/R WALL NADAPURAM SIDE

100%

0%

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

BEAM/SLAB  Staging Kainatty side

6

4

2

2

0

0

2

0

 

 

BEAM/SLAB  Bar bending and Fixing Kainatty side

6

4

2

2

0

0

2

0

 

 

BEAM/SLAB  Shuttering  and Concreting  Kainatty side

6

3

3

2

0

0

2

0

 

 

BEAM/SLAB  Staging Nadapuram side

9

7

2

1

0

0

1

0

 

 

BEAM/SLAB  Bar bending and Fixing Nadapuram side

9

7

2

2

1

0*

1

1

 

P7-P8 girder concrete completed.

BEAM/SLAB  Shuttering  and Concreting  Nadapuram side

9

5

4

2

1

0*

1

2

 

P8-P9 girder concrete complete

BEAM/SLAB KAINATTY  SIDE

6

3

3

2

0

0

2

0

 

 

BEAM/SLAB NADAPURAM SIDE

9

5

4

2

0*

0*

1

2

 

steel work of P7-P8 and P8-P9 slab in progress.

HR/FP/KERB KAINATTY  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

HR/FP/KERB NADAPURAM SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

  

 

 

Availability of Men               
Date 15-10-11 16-10-11 17-10-11 18-10-11 19-10-11 20-10-11 21-10-11
Nof labours 75 75 75 75 75 75 75 

 

Pile Concreting (Total no of piles - 45) completed  
Pile cap ( Total no. of pile cap 15) In progress Done 14 nos.
Pile cap at P4 location completed  
Pier concreting ( Total no. of pier  15) In progress Done- 13 no
Pier cap( Total no. of pier cap 15) In progress Done 12 nos
Slab concreting In progress Done 8 nos
Road work( diversion road) completed  
 RE wall panel casting (total 440) In progress Done 200 Nadapuram side, Done 200 Kainatty side
Hand rail casting horizontals In progress Done 600 nos.
P8-P9 girder  completed done concrete.
P7-P8 girder reinforcement completed  
P7-P8 girder shuttering In progress done concrete.
Excavation for pile cap at P6 location  completed  
RE wall excavation Nadapuram side In progress  
Repair work of diversion road In progress   
 
Back
 
    
P7-P8 GIRDER CONCRETE

    
    
P6 PILE CAP ACTIVITY

    
    
P3-P4 STAGING

    
    
EXCAVATION FOR RCC WALL -NADAPURAM SIDE

    
 
 
 

 

 

 

 

 

 

 