1
|
Works during this week
|
|
To divert the traffic in the site, the service road work is in progress at Petta side of ROB project.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2
|
Works proposed for next week
|
|
Mobilisation of Pilling equipments is in progress. Pre construction activities for piling work, Pilling.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3
|
Testing of Materials
|
|
Field Density test, Gredation test, Moisture content before compaction are Conducted
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4
|
Quality of work
|
|
Obtained test results are with in the permissible limit.
|
|
|
|
|
|
|
|
|
|
|
|
3
|
Remarks
|
|
At Anayara side of ROB ; the transformer shifted,Electric posts not shifted
|
|