Prevoius Weekly Reports

   Weekly progress report as on 21.10.2011
    
 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

1

PILE SHORNUR  SIDE

9

9

 

 

 

Completed

 

 

 

2

PILE M.C SIDE

36

36

 

 

 

Completed

 

 

 

 

3

PILE CAP SHORNUR SIDE

3

3

 

 

 

Completed

 

 

 

 

4

PILE CAP  M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

5

PIER SHORNUR  SIDE

3

3

 

 

 

Completed

 

 

 

 

6

PIER M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

7

PIER CAP SHORNUR  SIDE

3

3

 

 

 

Completed

 

 

 

 

8

PIER CAP M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

9

RE/R WALL SHORNUR SIDE

100%

37

63%

0

10.00%

4.00%

63.00%

10.00%

0

RCC wall concreting completed for a distance of 10 more metres

10

RE/R WALL M.C SIDE

100%

9

91%

0

15.00%

2.00%

13.00%

15.00%

0

PCC laying completed for one side for the RE panel erection.Shuttering work completed for the PCC laying at the other side

11

BEAM/SLAB SHORNUR  SIDE

3

2

1

0

0

0

0

0

0

 

12

BEAM/SLAB M.C SIDE

12

11

1

0

1

1

0

0

0

Miscellaneous works in progress..For the Inner kerb concreting at P3-P4,shuttering and reinforcement completed.Expansion joint concreting completed at P6 location.Handrail fixing completed at one side of P3-P4

13

HR/FP/KERB SHORNUR  SIDE

100%

50

50%

0

0.00%

0.00%

0.00%

0.00%

0 days

 

14

HR/FP/KERB M.C SIDE

100%

53

47%

0

8.00%

1.00%

6.00%

8.00%

 

inner kerb shuttering and reinforcement work completed at P3-P4.footpath slab reinforcement in progress

15

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

  

 

 

Availbility of Men               
Date 15-10-2011 16-10-2011 17-10-2011 18-10-2011 19/10/2011 20-10-2011 21-10-2011
Nof labours 18 0 9 7 8 7

 

Material Stocking Status      
  Required Available Remarks
Fine aggregate {cft} 300 300  
Cement(bag) 200 300  
Steel inT 5 10  
Coarse Aggreagate (cft) 300 340   

 

Utility shifting  
Utilities to be shifted  
BSNL COMPLETED
KSEB COMPLETED
KWA COMPLETED
Others COMPLETED 
 