   Weekly progress report as on 14.10.2011
    
Description Progress/Completed Remarks
Pier cap (Total no of pier Cap- 21) Completed  
RE Wall panel casting ( total 550 nos) Completed  
Slab calicut side  (total 10 nos ) In progress 9nos done
slab NH side ( 11 nos) In progress 9nos done
P12-P11 staging  completed  
P12-P11 girder reinforcement and shuttering Completed  
Retaining wall NH side In progress Done LHS -90%, RHS- 90%
Dirt wall AP1 concreting  In progress Done 90%
Handrail casting In progress 350 nos complete
Boring at RP1,RP4 pending design submitted by contractor for pile depth is not approved
NH side RE panel erection In progress  
RE wall excavation Calicut side Completed  
expansion joint at P18,P19,P17, P16,P15 and P14 Completed   

 

 
Back
 
    
RE WALL WORK.A2 SIDE.

    
    
RE WALL LEVELING PAD.

    
    
GIRDER REINFORCEMENT WORK IN P12-P11.

    
    
GIRDER BOTTOM IN P12-P11.

    
 
    
EXPANSION JOINT WORK IN P14.

    
    
EXPANSION JOINT WORK IN P13.

      
 

 

 

 

 

 

 

 