   Weekly progress report as on 14.10.2011
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE KUTTIPPURAM SIDE 33 0 33 6 0 0 6 0    
2 PILE KANJIPPURA SIDE 18 0 18 0 2 2 0 4   P11c ,P11 a pile complete
3 PILE CAP KUTTIPPURAM SIDE 11 0 11 0 0 0 0 0    
4 PILE CAP  KANJIPPURA SIDE 6 0 6 0 0 0 0 0    
5 PIER KUTTIPPURAM  SIDE 11 0 11 0 0 0 0 0    
6 PIER KANJIPPURA SIDE 6 0 6 0 0 0 0 0    
7 PIER CAP KUTTIPPURAM  SIDE 11 0 11 0 0 0 0 0    
8 PIER CAP KANJIPPURA SIDE 6 0 6 0 0 0 0 0    
9 RE/R WALL KUTTIPPURAM  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
  RE/R WALL KANJIPPURA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
11 BEAM/SLAB KUTTIPPURAM  SIDE 11 0 11 0 0 0 0 0    
12 BEAM/SLAB KANJIPPURA SIDE 6 0 6 0 0 0 0 0    
13 HR/FP/KERB KUTTIPPURAM  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
14 HR/FP/KERB KANJIPPURA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%     

 

 

Availbility of Men 

             
Date O8-10-2011 09-10-2011 10-10-2011 11-10-2011 12-10-2011 13-10-2011 14-10-2011
Nof labours 8 8 8 8 26 26 26 

 

 

Material Stocking Status

Required Available
Coarse Aggreagate (m3) available  
Fine Aggreagate(m3) available  
Cement(bag) 100 400
Steel(MT) available   

 

 