Progress Report of ROB Angadipuram as on 26-03-2016
 
Sl. No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week 
1 Pile 56 56 0 0 0 0 0 0
2 Pilecap 18 18 0 0 0 0 0 0
3 Pier 18 18 0 0 0 0 0 0
4 Piercap 16 16 0 0 0 0 0 0
5 Girders(span) 18 18 0 0 0 0 0 0
6 Deckslab 18 16 2 0 2 2 0 0
7 Expansion joint 19 16 3 0 3 3 0 0
8 Handrail-Bridge portion 18 18 0 0 0 0 0 0
9 Handrail-Approach portion 100% 100% 0% 0 0 0 0 0
10 Retaining wall-Perinthalmanna side-RHS 100% 100% 0% 0% 0% 0% 0% 0%
11 Retaining wall-Perinthalmanna side-LHS 100% 100% 0% 0% 0% 0% 0% 0%
12 Retaining wall-Angadipuram side-RHS 100% 100% 0% 0% 0% 0% 0% 0%
13 Retaining wall-Angadipuram side-LHS 100% 100% 0% 0% 0% 0% 0% 0%
14 Earth filling at Perinthalmanna and Angdipuram side 100% 100% 0% 0% 0% 0% 0% 0%
15 GSB & WMM Angadipuram side 100% 100% 0% 0% 0% 0% 0% 0%
16 GSB & WMM Perinthalmanna sideside 100% 0% 100% 0% 100% 100% 0% 0%
17 Painting 100% 80% 20% 0% 20% 10% 0% 10%
 