Work Planned upto 30.01.2010 |
Completed/Progress |
Delay |
RE wall works Medical College side |
Started |
Delay by the contractor - |
Fixing of panels 60mm length |
In progress |
|
Retaining wall on Shornur side |
Completed |
|
Approach slab |
Completed |
|
Friction slab |
Started |
|