   Weekly progress report as on 14.10.2011
    
 

Revised Progress Report For Mulankunnathukavu ROB for the week ending on 14-10-2011

 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

1

PILE SHORNUR  SIDE

9

9

 

 

 

Completed

 

 

 

2

PILE M.C SIDE

36

36

 

 

 

Completed

 

 

 

 

3

PILE CAP SHORNUR SIDE

3

3

 

 

 

Completed

 

 

 

 

4

PILE CAP  M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

5

PIER SHORNUR  SIDE

3

3

 

 

 

Completed

 

 

 

 

6

PIER M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

7

PIER CAP SHORNUR  SIDE

3

3

 

 

 

Completed

 

 

 

 

8

PIER CAP M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

9

RE/R WALL SHORNUR SIDE

100%

35

65%

0

10.00%

3.00%

63.00%

10.00%

0

RCC wall concreting completed for a distance of 6 more metres and shuttering and reinforcement work for 6 metres completed

10

RE/R WALL M.C SIDE

100%

9

91%

0

15.00%

2.00%

13.00%

15.00%

0

Earthwork excavation for the fixing of RE panels completed upto 90%.Erection of panels planned for the next week.Loading for the soil needed for backfilling in progress.

11

BEAM/SLAB SHORNUR  SIDE

3

2

1

0

0

0

0

0

0

 

12

BEAM/SLAB M.C SIDE

12

11

1

0

1

1

0

0

0

Miscellaneous works in progress.Work for the footpath started this week.Outer kerb concreting complted for all spans.Handrail fixing 90% completed.Inner kerb fixing in progress.

13

HR/FP/KERB SHORNUR  SIDE

100%

50

50%

0

0.00%

0.00%

0.00%

0.00%

0 days

 

14

HR/FP/KERB M.C SIDE

100%

52

48%

0

8.00%

2.00%

6.00%

8.00%

 

inner kerb concreting of one  more span completed ..ie (P5-P6) and( P5-P4.) ..footpath slab work in progress.Expansion joint concreting for the location P6 in progress.

15

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

  

 

 

Availbility of Men 

             
Date 10-08-2011 10-09-2011 10-10-2011 10-11-2011 10-12-2011 13-10-2011 14-10-2011
Nof labours 31 9 21 25 19 18 18 

 

 

Material Stocking Status

   
  Required Available
Fine aggregate {cft} 300 300
Cement(bag) 200 400
Steel inT 5 10
Coarse Aggreagate (cft) 300 340 

 

 

Utility shifting

 
Utilities to be shifted  
BSNL COMPLETED
KSEB COMPLETED
KWA COMPLETED
Others COMPLETED

 

 