   Weekly progress report as on 14.10.2011
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE CHERUVATHOOR  SIDE 27 21 6 2 0 0 0 0    
2 PILE PADANNA SIDE 24 6 18 0 0 1 0 1   P3 b pile complete
3 PILE CAP CHERUVATHOOR SIDE 27 0 27 0 0 0 0 0    
4 PILE CAP  PADANNA SIDE 24 0 24 0 0 0 0 0    
5 PIER CHERUVATHOOR SIDE 9 0 9 0 0 0 0 0    
6 PIER PADANNA SIDE 8 0 8 0 0 0 0 0    
7 PIER CAP CHERUVATHOOR SIDE 9 0 9 0 0 0 0 0    
8 PIER CAP PADANNA SIDE 8 0 8 0 0 0 0 0    
9 RE/R WALL CHERUVATHOOR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
10 RE/R WALL PADANNA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 0 9 0 0 0 0 0    
12 BEAM/SLAB PADANNA SIDE 8 0 8 0 0 0 0 0    
13 HR/FP/KERB CHERUVATHOOR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
14 HR/FP/KERB PADANNA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%     

 

 