   Weekly progress report as on 14.10.2011
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks 
1 PILE THRIKKARIPUR  SIDE 33 33 0 0 0 0 0 0  
2 PILE EZHIMALA SIDE 27 27 0 0 0 0 0 0  
3 PILE PAYYANNUR SIDE 27 27 0 0 0 0 0 0  
4 PILE CAP THRIKKARIPUR  SIDE 11 11 0 0 0 0 0 0  
5 PILE CAP EZHIMALA SIDE 9 9 0 0 0 0 0 0  
6 PILE CAP PAYYANNUR SIDE 9 9 0 0 0 0 0 0  
9 PIER THRIKKARIPUR  SIDE 11 11 0 0 0 0 0 0  
8 PIER EZHIMALA SIDE 9 9 0 0 0 0 0 0  
9 PIER PAYYANNUR SIDE 9 9 0 0 0 0 0 0  
10 PIER CAP THRIKKARIPUR  SIDE 11 11 0 0 0 0 0 0  
11 PIER CAP EZHIMALA SIDE 9 9 0 0 0 0 0 0  
12 PIER CAP PAYYANNUR SIDE 9 9 0 0 0 0 0 0  
16 RE/R WALL THRIKKARIPUR  SIDE 100% 50% 50% 0 0.00% 0.00% 0.00% 10.00%  
17 RE/R WALL EZHIMALA SIDE 100% 45% 55% 0 0.00% 0.00% 0.00% 0.00%  
18 RE/R WALL PAYYANNUR SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
19 BEAM/SLAB  Staging Thrikkaripur side 10 10 0 0 0 0 0 0  
20 BEAM/SLAB  Bar bending and Fixing Thrikkaripur side  10 10 0 0 0 0 0 0  
21 BEAM/SLAB  Shuttering  and Concreting  Thrikkaripur side 10 10 0 0 0 0 0 0  
22 BEAM/SLAB  Staging Ezhimala side 8 8 0 0 0 0 0 0  
23 BEAM/SLAB  Bar bending and Fixing Ezhimala side 8 7 1 1 1 1 0 0  
24 BEAM/SLAB  Shuttering  and Concreting  Ezhimala side 8 7 1 1 1 1 0 0 AP2-P16 slab complete
25 BEAM/SLAB  Staging Payyanur side 9 8 1 1 0 0 1 0  
26 BEAM/SLAB  Bar bending and Fixing Payyanur side 9 8 1 1 0 0 1 0  
27 BEAM/SLAB  Shuttering  and Concreting Payyanur side 9 8 1 1 0 0 1 0  
28 BEAM/SLAB THRIKKARIPUR  SIDE 10 10 0 0 0 0 0 0  
29 BEAM/SLAB EZHIMALA SIDE 8 7 1 1 1 1 0 0 AP2-P16 slab complete
30 BEAM/SLAB PAYYANNUR SIDE 9 8 1 1 0 0 1 0  
31 HR/FP/KERB THRIKKARIPUR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
32 HR/FP/KERB EZHIMALA SIDE 100% 0% 100% 0 0.00% 25.00% 0.00% 10.00% kerb 4 span complete-P10-P11,P11-P12,P12-P13,P13-P14
33 HR/FP/KERB PAYYANNUR SIDE 100% 30% 70% 0 10.00% 0.00% 0.00% 10.00% Handrail fixing on payyannur side planned
34 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%   

 

 

Availbility of Men 

           
Date O8-10-2011 09-10-2011 10-10-2011 11-10-2011 12-10-2011 13-10-2011 14-10-2011
Nof labours 65 65 65 65 65 65 65 

 

 

Material Stocking Status

   
  Required Available Remarks
Coarse Aggreagate (m3)   Available  
Fine Aggreagate(m3)   Available  
Cement(bag) 200 600  
Steel(MT) 5 30   

 

 