   Weekly progress report as on 14.10.2011
    
 

Si No

Activity Description

Total Quantity

Cumulative progress upto 13.10.11

Balance  work up to 13.10.11

Cumulative delay in Qty up to 13.10.11

Work  planned  during the week

Actual work done during the week

delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

1

PILE  Palarivattom side(Approach portion)

31

28

3

0

0

0

0

0

kwa line to be shifted

2

PILE Palarivattom side(railway portion)

6

0

6

0

0

0

0

0

"      "

3

PILE vytilla side(Approach portion)

42

0

42

0

0

0

0

0

"      "

4

PILE vytilla side(railway portion)

6

0

6

0

0

0

0

0

"      "

5

PILE CAP Palarivattom side(Approach portion)

8

7

1

1

1

1

0

0

"      "

6

PILE CAP Palarivattomside(railway portion)

1

0

1

0

0

0

0

0

"      "

7

PILE CAP vytilla side(Approach portion)

9

0

9

0

0

0

0

0

"      "

8

PILE CAP vytilla side(railway portion)

1

0

1

0

0

0

0

0

"      "

9

PIER Palarivattom side(Approach portion)

8

7

1

0

3

1

0

0

 

10

PIER Palarivattomside(railway portion)

1

0

1

0

0

0

0

0

 

11

PIER Vytilla side(Approach portion)

9

0

9

0

0

0

0

0

"      "

12

PIER vytilla side(railway portion)

1

0

1

0

0

0

0

0

"      "

13

PIER  CAP Palarivattom side(Approach portion)

8

7

1

0

0

0

2

2

 

14

PIER CAP Palarivattomside(railway portion)

1

0

1

0

0

0

0

0

 

15

PIER CAP  Vytilla side(Approach portion)

9

0

9

0

0

0

0

0

"      "

16

PIER CAP vytilla side(railway portion)

1

0

1

0

0

0

0

0

"      "

17

RE WALL PANEL

355

355

0

0

0

1

0

0

0

 Works at site

 

GIRDER  
A2 P15- Sheating Pipe laying in progress 
P15 P14-Reinforcement work  
P14 P13-Staging Work in progress  

 

 

Labour report

Date

07.09.11 08.10.11 09.10.11 10.10.11 11.10.11 12.109.11 13.10.11
Day Fri Sat Sun Mon Tue Wed Thurs
Climate sunny sunny sunny sunny sunny sunny sunny
No.of labours 26 24 11 21 22 22 22 

 

 

Availability of Material

 

Materials

Required for week ending on 20.10.11 Available as on 13.09.2011
Fine aggregate(M3) Ready Mix Concrete
Coarse aggregate(M3)
Cement(BAG)
Steel(TONN) 2 25 
 