Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 07.10.2011
    

 

shifting of utilities

In progress

 

KWA (PHED) sewage line

completed

 

  KWA Water supply line

completed

 

KSEB

In progress

complete on Petta side,90% completed on anayara side

transformer shifting on anayara side

In progress

 

BSNL

completed

 

Traffic Diversion

In progress

Service road (one side) on Pettaside in progress

 
Back
 
    
SECTIONING ROADWAY

    
    

    
    
AGGREGATE FOR GSB & WMM

      
 

 

 

 

 

 

 

 