ROB at Kunhipally
 

 

Sl.No.

Particulars

Details

1

Date of Tender Notification

10/8/2012

2

Date of opening of Tender

30/11/2012

3

Letter of Acceptance

22/01/2014

4

Date of agreement

12/02/2014

5

Notice to proceed issued

13/02/2014

6

Expected date of completion

31/03/2017

7

Contract amount(Rs)

11.73 Crore

8

up todate Utility shifting and consultancy charges

13,49,997.00

9

up todate LA cost (Rs)

1,58,37,388.00

10

Period of completion

15 months

11

LC. No

217

12

Location

Between Mukali and Mahe

13

Contractor

M/s Skilled Construction Company Ltd

14

Project Management Consultant

M/s KITCO Ltd

15

Length of structure(m)

573.43

16

Length of Railway Portion (Not within the scope of RBDCK)(m)

77.2

17

Length  towards  NH side

217.5

18

Length  towards Mondhal Bridge side

278.73

19

Slope of ROB towards NH side

1 in 20

20

Slope of ROB towards Mondhal Bridge side

1 in 25

21

Width of carriage way

7.5 m

22

Foot Path

Nil

23

Total width of bridge including crash barriers

8.5 m

 

 

Status of Kunhippally ROB as on 31- 12-2016

All superstructure works completed.

The work of approach portion on NH side is pending due to non availability of land.
 

 

 

 

 

 

 

 

 

 

 