Sl.No.
|
Particulars
|
Details
|
1
|
Date of Tender Notification
|
10/8/2012
|
2
|
Date of opening of Tender
|
30/11/2012
|
3
|
Letter of Acceptance
|
22/01/2014
|
4
|
Date of agreement
|
12/02/2014
|
5
|
Notice to proceed issued
|
13/02/2014
|
6
|
Expected date of completion
|
31/03/2017
|
7
|
Contract amount(Rs)
|
11.73 Crore
|
8
|
up todate Utility shifting and consultancy charges
|
13,49,997.00
|
9
|
up todate LA cost (Rs)
|
1,58,37,388.00
|
10
|
Period of completion
|
15 months
|
11
|
LC. No
|
217
|
12
|
Location
|
Between Mukali and Mahe
|
13
|
Contractor
|
M/s Skilled Construction Company Ltd
|
14
|
Project Management Consultant
|
M/s KITCO Ltd
|
15
|
Length of structure(m)
|
573.43
|
16
|
Length of Railway Portion (Not within the scope of RBDCK)(m)
|
77.2
|
17
|
Length towards NH side
|
217.5
|
18
|
Length towards Mondhal Bridge side
|
278.73
|
19
|
Slope of ROB towards NH side
|
1 in 20
|
20
|
Slope of ROB towards Mondhal Bridge side
|
1 in 25
|
21
|
Width of carriage way
|
7.5 m
|
22
|
Foot Path
|
Nil
|
23
|
Total width of bridge including crash barriers
|
8.5 m
|
|
|
Status of Kunhippally ROB as on 31- 12-2016
All superstructure works completed.
The work of approach portion on NH side is pending due to non availability of land.
|