Work Planned upto 06.03.2010 |
Completed/Progress |
Remarks |
Staging work for P3-P4 Span |
Not started |
Road Blocked for P3-P4 span work. |
P4-P5 Span Staging work removal |
In Progress |
|
Cross beam & slab concreting of P4-P5 Span |
Completed |
|
Approval of GAD by railways- follow up to be done by contractor |
|
Delay in GAD approval |
Box culvert works (under pass) |
Not started |
Contractor agreed to start under pass, water line and telephone line to be shifted for excavation |