Description
|
Progress/Completed
|
Remarks
|
Pile concreting
|
in progress
|
Done 27nos
|
AP2,P15,P13 consolidation and marking
|
completed
|
|
Building demolition at P2,P3 location
|
In progress
|
90% complete
|
building demolition at P4 location
|
completed
|
|
Demolition of 2 shops in P6 location
|
Completed
|
|
KSEB utility shifting near AP2
|
Completed
|
|
BSNL OFC cable shifting
|
In progress
|
|
pile chipping at AP2
|
In progress
|
|
Rig shifting in P3 location
|
completed
|
|
Pile load test bed preparation at P7 location
|
In progress
|
|