   Weekly progress report as on 07.10.2011
    

 

Description Progress/Completed Remarks

Pile concreting

In progress

Done 16 nos(P10c,P12c complete this week)

Site level survey

completed

 

7 day Cube test

Completed

 

BSNL, KWA site inspection for utility shifting

In progress

 

KSEB site inspection for utility shifting

completed

 

KSEB utilities estimate

In progress

almost complete

site clearing in thamarassery area

In progress

 

filling work towards thamarassery side

In progress

60m complete

filling work in piling location

Completed

uptoAP2 area

 