Description |
Progress/Completed |
Remarks |
Pile concreting
|
In progress
|
Done 16 nos(P10c,P12c complete this week)
|
Site level survey
|
completed
|
|
7 day Cube test
|
Completed
|
|
BSNL, KWA site inspection for utility shifting
|
In progress
|
|
KSEB site inspection for utility shifting
|
completed
|
|
KSEB utilities estimate
|
In progress
|
almost complete
|
site clearing in thamarassery area
|
In progress
|
|
filling work towards thamarassery side
|
In progress
|
60m complete
|
filling work in piling location
|
Completed
|
uptoAP2 area
|