Prevoius Weekly Reports

   Weekly progress report as on 07.10.2011
    

 

Pile Concreting (44 nos)

completed

Done 44 nos

Pile cap

In progress

done 8 nos(P2  pile cap complete this week)

Pile load test P7 b

completed

 

Pier

In progress

done 3nos-P9,P8,P7

Pier cap

In progress

done 1 no

Retaining wall RCC footing in puliyanam side

In progress

Done 15m, 15m first lift complete

Retaining wall puliyanam side

In progress

15m third lift complete

Dirt wall work

In progress

 

Extension of culvert slab over irrigation canal

completed

 

Drain work

In progress

NH side remaining

KSEB overhead electric line shifting NH side

completed

 

Utilities (KWA) in Puliyanam side

completed

 

Cutting, bending and placing of reinforcement for Base slab and side wall of drain

completed

 

 Excavation for drain 15m . (NH Side)

completed

 

PCC for drain 30.0m . (NH side )

completed

 

 Base slab of drain 35m  (Puliyanam side)

completed

 

 