Pile Concreting (44 nos)
|
completed
|
Done 44 nos
|
Pile cap
|
In progress
|
done 8 nos(P2 pile cap complete this week)
|
Pile load test P7 b
|
completed
|
|
Pier
|
In progress
|
done 3nos-P9,P8,P7
|
Pier cap
|
In progress
|
done 1 no
|
Retaining wall RCC footing in puliyanam side
|
In progress
|
Done 15m, 15m first lift complete
|
Retaining wall puliyanam side
|
In progress
|
15m third lift complete
|
Dirt wall work
|
In progress
|
|
Extension of culvert slab over irrigation canal
|
completed
|
|
Drain work
|
In progress
|
NH side remaining
|
KSEB overhead electric line shifting NH side
|
completed
|
|
Utilities (KWA) in Puliyanam side
|
completed
|
|
Cutting, bending and placing of reinforcement for Base slab and side wall of drain
|
completed
|
|
Excavation for drain 15m . (NH Side)
|
completed
|
|
PCC for drain 30.0m . (NH side )
|
completed
|
|
Base slab of drain 35m (Puliyanam side)
|
completed
|
|