SlNo
Activity –which can be completed without caution
Description
Total Quantity
Cumulative progress up to this week
(1)
Balance work
(2)
Cumulative delay in weeks after
Spplagmnt
(3)
Work planned during the week
(4)
Actual work done during the last week
(5)
Short fall in the last week
(6)
Work
Planned for next week
(7)
No of days remaining for completion as per the weekly plan
Remarks
1
Re wall towards NH side
100%
34
66
32
0
.
3
Approach
Span
5
37
-
4
Pier cap
2
46
Pile (Rly)pulikakadavuside
60
6
Pile (Rly)Nhside
Piers (Rly)
51
9
R0AD WORK
{WBM} towards pulikkakadavuside
90
1O
Kerb/handrail (approach portion)N.H side
200m
Inner kerbconcreting complete for a distance of 25 metres.Handrailposts concreted for a. distance of 50 metres.Nowork in the last week.
Nil
12
Friction slab approach portion(N.H side
No work in the last week
Material Stocking Status
Coarse Aggreagate (m3)
17
Fine Aggreagate(m3)
15
Cement(bag)
8
13
Steel(MT)
10
RE blocks
2150 available at site
Utility shifting
Utilities to be shifted
Status
BSNL
KSEB
nohindrance
KWA
Others
No hindrance
Sl.
No
Date
Activity
1-10-2011
Boring of the pile at location P8/2
2-10-2011
Boring of the pile at P8/2
3-10-2011
Boring of the pile at P8/2.
4-10-2011
Concreting of the pile P8/2
7
5-10-2011
6-10-2011
7-10-2011
No work. Poojaholidays
..
Rig shifting and centering to location P8/1. and boring at P8/1
Boring at P8/1 in progress