Prevoius Weekly Reports

   Weekly progress report as on 07.10.2011
    

 

Revised Progress Report For Mulankunnathukavu ROB for the week ending on 07-10-2011

 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

1

PILE SHORNUR  SIDE

9

9

 

 

 

Completed

 

 

 

2

PILE M.C SIDE

36

36

 

 

 

Completed

 

 

 

 

3

PILE CAP SHORNUR SIDE

3

3

 

 

 

Completed

 

 

 

 

4

PILE CAP  M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

5

PIER SHORNUR  SIDE

3

3

 

 

 

Completed

 

 

 

 

6

PIER M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

7

PIER CAP SHORNUR  SIDE

3

3

 

 

 

Completed

 

 

 

 

8

PIER CAP M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

9

RE/R WALL SHORNUR SIDE

100%

40

60%

0

10.00%

3.00%

56.00%

10.00%

0

RCC wall shuttering and reinforcement for a distance of  10 metres more

10

RE/R WALL M.C SIDE

100%

9

91%

0

0.00%

7.00%

0.00%

15.00%

0

Earthwork excavation for the fixing of RE panels for a distance of  20 metres at 11 metres width.

11

BEAM/SLAB SHORNUR  SIDE

3

2

1

0

0

0

0

0

0

 

12

BEAM/SLAB M.C SIDE

12

10

2

0

1

1

0

0

0

beam and deck slab concreting of P3-P4 completed .Thus concreting of all spans except the adjacent spans have been completed.Dirt wall concreting of AP2 completed.

13

HR/FP/KERB SHORNUR  SIDE

100%

50

50%

0

0.00%

0.00%

0.00%

0.00%

0 days

 

14

HR/FP/KERB M.C SIDE

100%

50

50%

0

8.00%

2.00%

6.00%

8.00%

 

inner kerb concreting of one  more span completed ..ie (P6-P7. Handrail fixing of one side of P5-P4 completed..shuttering and reinforcement for the footpath slab started.at AP2-P13

15

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

 

Availbility of Men

 

 

 

 

 

 

 

Date

10-01-2011

10-02-2011

10-03-2011

10-04-2011

10-05-2011

10-06-2011

10-07-2011

Nof labours

34

0

31

35

36

21

30

 

Material Stocking Status

 

 

 

 

 

 

Required

Available

Remarks

 

 

Fine aggregate {cft}

300

300

 

 

 

Cement(bag)

200

50

stock will be replendished tomorrow

 

 

Steel inT

5

8

 

 

 

Coarse Aggreagate (cft)

300

340

 

 

 

 

Utility shifting

 

Utilities to be shifted

 

BSNL

COMPLETED

KSEB

COMPLETED

KWA

COMPLETED

Others

COMPLETED

 