Work Planned upto 20.03.2010 |
Completed/Progress |
Remarks |
Staging work for P3-P4 Span |
Completed |
Road Blocked for P3-P4 span work. |
Shuttering and reinforcement for No.1 girder |
In progress |
|
Approval of GAD by railways- follow up to be done by contractor |
|
Delay in GAD approval |
Box culvert works (under pass) |
Not started |
Contractor agreed to start under pass,utilities are shifting from the site |