Untitled Document
Road to Prosperity
Site last updated on: 12-12-2020 | You are visitor:
7886345
Contact Us
Login
Home
About Us
Vision
Profile
Board of Directors
Organization Chart
Staff Profile
Articles Of Association
Projects
At a Glance
Completed Projects
Projects Under Construction
Tendering stage
Land Acquisition in Progress
DPR under KIIFB review
DPR under preparation
Toll Collection
KIIFB Projects
Acts & Rules
Right to Information
Tenders
Corporate Governance
Annual Accounts
Annual Reports
Photo Gallery
Completed Projects
Projects Under Construction
Citizen Services
Careers
Right to Service
Weekly Reports
|
Photo Album
10.12.2010
PROGRESS OF ROB and ROAD WORK AS ON 10-12.2010
Description
Completed/ Progress
Remarks
ROB at Backel
Painting of bridge
completed
Toll booth work
completed
Road Work
In progress
BM completed, BC work planned on 12/12/10
Click here to view Previous Reports
ROB AT BAKEL
PREPARATION FOR MASTIC ASPHALT(2010.11.18)
APPROACH TOWARDS KASERGODE SIDE(2010.11.18)