Name |
ROB at Bakel |
L.C No |
276 |
Rly Km No. |
825/15 |
Location |
Pallikkara and Kottikkulam Rly Stations |
Project management
Consultant and Supervision |
M/s KITCO Ltd. |
Funding |
Loan from HUDCO |
Length including approaches |
468.74 m |
Number of Spans |
11 |
Clear Road Way |
7.5 m |
Footpath |
1.5 m |
Contractor |
1. M/s Vijay Nirman Company Pvt Ltd.
2. M/s C.V. Thomas |
Status |
Work completed and ROB inaugrated on 16.12.2010 |
Date of Commencement |
02.05.2002 |