Prevoius Weekly Reports
|
22.7.2010 |
|
ROB at Bakel
PROGRESS OF ROB WORK AS ON 17.7.2010 |
Work Planned upto 17/7/2010 |
Completed / Progress |
Remarks |
Span of Kasargod side |
|
|
Concreating Beam and Slab |
Completed |
|
Outer Kerb Casting |
Completed |
|
Removal of Shuttering |
In progress |
|
Hand rail casting |
In progress |
|
|
|