   Weekly progress report as on 30.09.2011
    

 

Description Progress/Completed Remarks

ROB KOILANDY

 

 

Pile concreting

In progress

Done 14 nos(P10a,P12a complete this week)

Site level survey

completed

 

7 day Cube test

Completed

 

BSNL, KWA site inspection for utility shifting

In progress

 

KSEB site inspection for utility shifting

completed

 

KSEB utilities estimate

In progress

almost complete

site clearing in thamarasseryarea

In progress

 

filling work towards thamarasseryside

In progress

60m complete

filling work in piling location

Completed

uptoAP2 area

 
Back
 
    
PILE 11C CAGE INSERTING

    
    
PILE 12A BORING

    
    
PILE 10A BORING

    
    
FILLING WORKS TOWARDS THAMARASSERY SIDE IN PROGRESS

    
 
    
PILE 12A CONCRETING

      
 

 

 

 

 

 

 

 