Prevoius Weekly Reports

   weekly progress as on 30.9.2011
    

 

Progress Report For Pulianam  ROB for the week ending on 29.9.2011                     
Sl No   Activity Description   Total Quantity  Cumulative progress upto last week   Balance  work up to last week  Cumulative delay in Qty up to last week  Work  planned  during the week   Actual work done during the week   Cumulative delay in Qty up to this week  Work  Planned for next week   Remarks 
1 Pile towards NH side 26 26 0 0 0 0 0 0 TARGET ACHIEVED
2 Pile towards Puliyanam side 18 18 0 0 1 1 0 0 TARGET ACHIEVED
3 Pile cap at NH  Side 6 5 1 0 1 1 0 0  
4 Pile Cap at Pulianam side 4 3 1 0 1 0 1 1  
5 RC wall at Puliyanam side 100% 20% 80% 0 0% 0% 0% 0%  
6 Pier at NH Side 6 4 2 0 0 0 0 0  
7 Pier at Puliyanam Side 4 1 3 0 1 0 1 1  
                     
Date 24.09.2011 26.09.2011 27.09.2011 28.09.2011 29.09.2011 30.09.2011        
Climate pleasant pleasant pleasant pleasant pleasant pleasant        
No.of labours 42 42 48 48 48 65        
                     
                     
availability of material                  
materials Required Available                
Fine aggregate(M3) 10 15                
Coarse aggregate(M3) 15 15                
Cement(BAG) 300 600                
Steel(TONN) 5 20                
 
Back
 
    
P10 EARTH WORK FOR PILE CAP.24.09.2011

    
    
P3 PIER CAP REINFORCEMENT WORK.29.09.2011

    
    
P1 PILE CAP REINFORCEMENT WORK 23.09.2011

    
    
DEVIATION ROAD RECTIFIED .30.09.2011

    
 
    
P8 PIER CAP CONCRETE.30.09.2011

    
    
RC WALL SHUTTERING 3RD LIFT.24.09.2011

      
 

 

 

 

 

 

 

 