Prevoius Weekly Reports

   Weekly progress report as on 30.09.2011
    

 

Progress Report For Palakkad Sultanpet ROB for the week ending on 30-09-2011

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

1

PCC for RAFT MOYAN SIDE

1

1

0

0

0

0

0

0

 

 

2

PCC for RAFT PALAKKAD SCHOOL SIDE

3

3

0

0

0

0

0

0

 

 

3

RAFT PALAKKAD SIDE

1

1

0

0

0

0

0

0

 

 

4

RAFT MOYAN SCHOOL SIDE

3

3

0

0

0

0

0

0

 

 

5

PIER PALAKKAD SIDE

1

1

0

0

0

0

0

0

 

 

6

PIER MOYAN SCHOOL SIDE

3

3

0

0

0

0

0

0

 

 

7

PIER CAP PALAKKAD SIDE

1

1

0

0

0

0

0

0

 

 

8

PIER CAP MOYAN SCHOOL SIDE

3

3

0

0

0

0

0

0

 

 

9

RE/R WALL PALAKKAD  SIDE

100%

60%

40%

0

0.00%

0.00%

0.00%

0.00%

 

 

10

RE/R WALL MOYAN SCHOOL SIDE

100%

48%

52%

0

0.00%

0.00%

0.00%

0.00%

 

 

11

BEAM/SLAB  Staging Palakad  SIDE

4

4

0

0

0

0

0

0

 

 

12

BEAM/SLAB  Bar bending and Fixing Palakad  SIDE

4

3

1

0

1

1

0

0

 

 bar bending forP4-RP1 slab completed

13

BEAM/SLAB  Shuttering  and Concreting Palakad SIDE

4

3

1

0

1

1

0

0

 

P4-RP1 slab casted

14

BEAM/SLAB  Staging Moyan schoolSIDE

5

5

0

0

0

0

0

0

 

 

15

BEAM/SLAB  Bar bending and Fixing Moyan school SIDE

5

5

0

0

0

0

0

0

 

 

16

BEAM/SLAB  Shuttering  and Concreting  Moyan school  SIDE

5

5

0

0

0

0

0

0

 

 

17

BEAM/SLAB PALAKKAD  SIDE

4

3

1

0

1

1

0

0

 

 

18

BEAM/SLAB MOYAN SCHOOL SIDE

5

5

0

0

0

0

0

0

 

 

19

BEAM/SLAB RAILWAY SPAN

7

0

7

1

0

0

1

0

 

 

20

HR/FP/KERB PALAKAD  SIDE

100%

5%

95%

0

5.00%

5.00%

0.00%

5.00%

 

P4-RP1 kerb casting completed on both sides,P1-P2 both side handrail fixing complete

21

HR/FP/KERB NH SIDE

100%

45%

55%

0

0.00%

0.00%

0.00%

0.00%

 

 

22

HR/FP/KERB RAILWAY SPAN

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

23

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

 

 

Material Stocking Status

 

Required

Available

Fine aggregate {m³}

8

20

Cement(bag)

200

320

Steel in T

3

78

Coarse aggregate (m3)

 10

 28

 
Back
 
    
RP5-RP6 STAGING WORK

    
    
P7-P8 CANTILEVER CASTING

    
    
P4-RP1 DECK SLAB CASTING

    
    
P1-P2 HANDRAIL FIXING

    
 
    
P1-P2 CANTILVER STAGING

    
    
HANDRAIL CASTING

    
    
BARBENDING OF P4-RP1 SLAB

    
 
 
 

 

 

 

 

 

 

 