   weeekly progress
    

 

Progress Report For Parappanangadi ROB for the week ending on 30-09-2011
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE CALICUT  SIDE 30 30 0 0 0 0 0 0    
2 PILE NH SIDE 33 33 0 0 0 0 0 0    
3 PILE RAILWAY SPAN 20 0 20 20 0 0 20 0    
4 PILE CAP CALICUT  SIDE 10 10 0 0 0 0 0 0    
5 PILE CAP NH SIDE 11 11 0 0 0 0 0 0    
6 PILE CAP RAILWAY SPAN 4 0 4 3 2 0 4 4    
7 PIER CALICUT  SIDE 10 10 0 0 0 0 0 0    
8 PIER NH SIDE 11 11 0 0 0 0 0 0    
9 PIER RAILWAY SPAN 4 0 4 4 0 0 4 0    
10 PIER CAP CALICUT  SIDE 10 10 0 0 0 0 0 0    
11 PIER CAP NH SIDE 11 11 0 0 0 0 0 0    
12 PIER CAP RAILWAY SPAN 4 0 4 4 0 0 4 0    
13 RE/R WALL CALICUT  SIDE 100% 0.00% 100% 0 0.00% 0.00% 0.00% 0.00%    
14 RE/R WALL NH SIDE 100% 90.00% 10% 0 0.00% 0.00% 0.00% 0.00%    
15 BEAM/SLAB  Staging CALICUT  SIDE 10 9 1 0 0 0 0 0    
16 BEAM/SLAB  Bar bending and Fixing CALICUT  SIDE 10 9 1 0 0 0 1 0    
17 BEAM/SLAB  Shuttering  and Concreting  Calicut SIDE 10 9 1 0 0 0 0 o    
18 BEAM/SLAB  Staging NH SIDE 11 9 2 2 1 0* 1 1   P11-P12 staging in progress
19 BEAM/SLAB  Bar bending and Fixing NH  SIDE 11 8 3 3 1 0* 3 1   P10-P11 girder reinforcement complete
20 BEAM/SLAB  Shuttering  and Concreting  NH  SIDE 11 8 3 1 0 0* 3 1   P10-P11 girde r concrete complete
21 BEAM/SLAB CALICUT  SIDE 10 9 1 1 0 0 1 0    
22 BEAM/SLAB NH SIDE 11 8 3 1 0 0 0 0    
23 BEAM/SLAB RAILWAY SPAN 3 0 3 0 0 0 0 0    
24 HR/FP/KERB CALICUT  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
25 HR/FP/KERB NH SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
26 HR/FP/KERB RAILWAY SPAN 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
27 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
                       
 