Work Planned upto 03.04.2010 |
Completed/Progress |
Remarks |
Concreting 2 girders |
Completed |
|
Staging work for P3-P4 Span |
Completed |
Road Blocked for P3-P4 span work. |
Shuttering and reinforcement for No.3 girder |
In Progress |
|
Approval of GAD by railways- follow up to be done by contractor |
|
Delay in GAD approval |
Box culvert works (under pass) |
Not started |
Contractor agreed to start under pass, water line and telephone line shifted for excavation work not started due to labour shortage. |